ROCKY POINT — The $375,000 replacement of the Rocky Point Bridge on Route 19 is now complete and the bridge will open to the public at 4 p.m. on Friday.

 

Data collector Mike Cleveland (left), Transportation and Infrastructure Renewal Minister Robert Vessey, and Project Manager Vince Morrison on the site of the new Rocky Point Bridge. 
 

Construction of the project began in June following a community information session in New Dominion. The original bridge was built in 1959.

One more bridge will be replaced in 2014-15 in Souris.

 